If you're the person holding the purchase order for a pneumatic conveying system—but you're not the engineer who can rattle off the difference between dilute and dense phase without checking—this checklist is for you.

Seven steps. Each one has a checkpoint you can verify without an engineering degree. Some need your technical team's sign-off, but the coordination piece is squarely on procurement. That's you.

I'm the procurement coordinator at a 240-person industrial processing company. I manage roughly $320,000 in annual equipment orders across 10 vendors, and I report to both operations and finance. When a system shows up wrong or a warranty dispute drags on, I'm the one caught in the middle. This checklist came from the times it didn't exist.

When This Applies

You're sourcing a pneumatic conveying system—dilute phase, dense phase, vacuum, or powder handling—and your job is the procurement side: getting quotes, coordinating technical review, managing documents, and making sure the equipment actually arrives and works.

You can't validate airflow calculations yourself. Fine. This checklist is about making sure the right information moves between the right people—before money changes hands.

Step 1: Get the Material Profile in Writing

Before you request a single quote, ask operations or engineering for a one-page material profile. Not "polymer pellets." Specific: bulk density, particle size range, moisture content, temperature at the feed point, abrasive or corrosive properties, and whether the dust is combustible.

Why does procurement care about moisture content? Because when a manufacturer quotes off a vague description, they assume the easiest possible conditions. The quote comes back low. The system gets built. And then it clogs or wears out in six months because nobody accounted for the material's actual behavior.

I learned this the hard way. In 2023, we sourced a powder pneumatic conveying system based on a three-line email description. The quote looked great. The system couldn't handle our material's moisture level. Retrofitting the air dryer alone cost us $6,800—more than the original quote's line item for the dryer we didn't include.

Checkpoint: You have a signed material profile document. Not an email thread. A document.

Step 2: Define Capacity, Distance, and Layout

Get the numbers in writing: throughput (tons per hour), horizontal and vertical conveying distance, number of bends, feed points, discharge points, and any space constraints at the installation site.

This is where procurement can actually add value. If three vendors each quote based on different assumptions, the prices aren't comparable. At all. And comparing non-comparable quotes is how you end up selecting the wrong vendor for the wrong reasons.

Insist that every quote includes a scope summary listing the assumptions it's based on. If a vendor won't provide that, that tells you something too.

Checkpoint: A layout sketch with dimensions, signed off by whoever owns the plant floor.

Step 3: Let Engineering Pick the Phase Type—But Verify They Did

Dilute phase vs. dense phase. Pressure vs. vacuum. This is an engineering decision based on the material profile and distance. Your job is not to pick—it's to confirm that someone did, and that the reasoning is documented.

Here's the trap: some vendors push whatever they specialize in, regardless of your material. If one vendor recommends dilute phase and another recommends dense phase for the same application, you have a technical disagreement. Route it back to engineering before you move forward. Don't let two incompatible quotes sit side by side in a comparison spreadsheet like they're equivalent options.

The exception is vacuum versus pressure. There, the choice often comes down to plant layout and where you can put the blower. Both can work. Then it's a legitimate procurement comparison.

Checkpoint: Engineering's phase recommendation is in writing, with a one-paragraph rationale.

Step 4: Verify the Manufacturer's Experience With Your Material

A manufacturer who has built 200 pneumatic conveying systems for grain may not be the right fit for a fine, abrasive, or combustible powder. Ask for three references from projects with a similar material and a similar conveying challenge. Then actually call them.

And here's the part most people skip: ask each reference the same question—what went wrong? Nobody's system is perfect. How the vendor handled problems matters more than whether problems existed.

I used to believe reference checks were a formality. Skip them and save a week, right? Then we picked a vendor whose references we never called. Solid delivery record, they said. What they didn't say was that their after-sales support response time averaged two weeks. Our first maintenance issue cost us nine production days. That's not a formality—that was a $23,000 lesson.

Checkpoint: You've spoken to at least one reference by phone and documented what they said.

Step 5: Compare Total Cost of Ownership, Not Quotes

The sticker price is the smallest part of the equation. For a pneumatic conveying system, the five-year cost includes power consumption, wear parts (bends, rotary valves, filter bags), scheduled maintenance, and spare parts availability.

Build a simple spreadsheet with a five-year view for each vendor. Ask every vendor for estimated power draw at your operating conditions, recommended maintenance intervals, and the cost of a standard wear-parts kit. If a vendor can't or won't provide these numbers, that's a data point.

Not every vendor will cooperate. Some will claim their systems don't need wear parts, which—for abrasive powders—is not a real answer. Note it and move on.

Checkpoint: A five-year TCO comparison with the same cost categories for every vendor.

Step 6: Lock Down Compliance and Documentation Requirements

If your material is a combustible dust—and many powders are—you'll need documentation that the system meets applicable standards. In the US, that's typically NFPA 652 (combustible dust fundamentals) and NFPA 660 for the conveying equipment itself. In the EU, it's ATEX directives and CE marking.

Don't wait until after the PO is issued to ask for these. Compliance documents have a way of being "in progress" for six months after delivery. Write the list into the purchase agreement: material certificates, test reports, O&M manuals, spare parts lists, electrical schematics.

Note to self: I should really build a standard documentation checklist template so I stop re-typing this email every time.

Checkpoint: The documentation list is attached to the PO, not buried in an email chain.

Step 7: Define Invoicing and Payment Milestones Up Front

Milestone-based payments protect both sides. Typical structure for equipment orders: 30% on PO, 40% on shipment, 20% on installation, 10% on acceptance testing. Adjust for your situation, but never pay 100% before the system runs.

And confirm the vendor can issue a proper commercial invoice with your PO number, tax documentation, and correct billing entity. Trust me on this one—our finance team rejected a $47,000 invoice once because the vendor used a different legal entity name than what was on the PO. The payment was delayed three weeks, and the vendor—reasonably—paused the shipment.

Checkpoint: Written agreement on payment milestones and invoicing requirements, signed by finance if necessary.

Common Mistakes to Avoid

Accepting verbal scope confirmations. If it's not in the quote document, it doesn't exist. "We'll include the controls" means nothing when the invoice for controls shows up separately.

Comparing quotes with different scopes. Two numbers on a spreadsheet aren't comparable if Vendor A included installation and Vendor B didn't. Normalize the scope first, then compare.

Skipping the site survey. Some manufacturers require it. Some don't, but should. If your layout has anything unusual—tight bends, low ceiling clearance, limited utility access—get someone to walk the site before the quote is finalized.

Forgetting the pre-shipment inspection. For custom equipment, arrange a factory acceptance test (FAT) before shipment if at all possible. Catching a problem at the factory costs a fraction of fixing it on-site.

Bottom line: the technical evaluation belongs to engineering. The process—making sure information flows, quotes are comparable, documents are complete, and payments are structured—that's procurement's job. Get that right, and the system has a much better chance of arriving on time, working as specified, and staying under budget.